Center Streetscape Project

Rendering of completed Center Streetscape

Lexington Center Streetscape Open for Business! Safer. Brighter. Together.

COMMUNICATION

Stay Up-To-Date with
Streetscape e-newsletter
Have a specific concern?
Email us
Need immediate help during construction?
Call 781-274-8305

VIEW: Interactive map showing current and upcoming work zones

TREES: Learn how this project is improving tree health in Lexington Center

Construction Update: Week of May 23-27

Work zones will be contained to zones on the north side of the street from:

  • Meriam Street to Depot Square (Eastern Bank)
  • Edison Way to Waltham Street (CVS)
  • Waltham Street (CVS) to Depot Square

See the current workzone maps. 

Installation of the final brick walking surface will begin Monday, May 23. Installation of final brick will follow excavation and installation of temporary concrete walking surface for the duration of the project.

It is anticipated that work over the next 4-6 weeks will likely be the heaviest construction activity that we will see during the project. There will be a lot of activity in the construction zones. After that, construction disruption will lessen to a degree, but will remain consistent and ongoing until the end of the construction season. 

As always, access to businesses will REMAIN OPEN AT ALL TIMES. Please remember to check our interactive map for the latest construction work zones.

The Project in a Nutshell 

Map of Mass. Ave from Library to Woburn StreetThe Center Streetscape Project includes streets and sidewalks along Massachusetts Avenue from Clarke Street (next to the Library), to near the Police Station Driveway (see map at right).

Reconstruction of the Woburn Street/Massachusetts Avenue intersection is not a part of this project.