Frequently Asked Questions

Updated 5-3-2020

What are the limits of the project? 
The project extends from the Massachusetts Avenue / Meriam Street / Clarke Street intersection to approximately the Police Station Driveway.

Are the roadways adjacent to the Battle Green part of the same project? 
The Battle Green project is separate from the Center Streetscape Project.

Has the Woburn Street / Massachusetts Avenue intersection been removed from this project? 
Yes.

Has the redesign followed the recommendation of the Center Streetscape AdHoc Committee Report?
Yes.  The redesign is following the recommendations of the AdHoc Committee that were approved by the Select Board.

What is the schedule for the project?
The project is scheduled to begin in mid-late May 2021.

How long will construction take? 
The construction is expected to take 2 years to complete and will be performed in phases to minimize disruption as much as possible.

I directly abut the project with my business, how will I be informed of the construction impacts and progression?
The town will be working directly with the contractor and the resident engineer (project inspector) throughout the project to get advance notice of expected work.  There will be contact with the abutters through the website, emails and direct interaction.  The communication plan is being developed and we will be reaching out this winter with more detail and how to stay informed throughout the project.